Sewerage Connection

Obtaining Sewerage Connection

Name of the Department KARNATAKA INDUSTRIAL AREA DEVELOPMENT BOARD
Name of the Service Obtaining Sewerage Connection
Whom to approach for this service (Designated Officer)? Executive Engineer in Zonal offices
Procedure involved to get this service Applying Online in KIADB website
Form to be submitted to get this service
Who are eligible to get this service Citizen/ Public
Documents to be enclosed with the request
Fee/Charges to be paid to get the service NIL
Maximum number of days to wait to get this service delivered 7 Working Days
Whom to approach as a appeal (Competent Officer), if the service is not delivered in time
or rejected by officer
Chief Engineer
Maximum number of days to wait to get the decision of the Competent Officer 7 Working Days
Whom to approach as 2nd appeal (Appellate Authority), if the decision of the Competent
officer is not acceptable or not implemented?
Chief Executive Officer and Executive Member
Maximum no. of days to wait to get the decision of Appellate Authority 10 Working Days
Other information Online Services
Website (if online) www.KIADB.in
Reference Document

Work Flow

Step Description No. of Days Designation
1 RECEIVING AND VERIFICATION OF APPLICATION DOCUMENTS 4.0 Assistant Engineer
2 SCRUTINY OF APPLICATION 2.0 Assistant Engineer
3 SCRUTINY AND APPROVAL OR REJECTION OF APPLICATION 1.0 Asst. Executive Engineer