Officer, Appellate Authority and time limit for disposal of Appeal of KIADB
Sl.No | List of Services | Designated Officer | Time limit for Disposal by the Designated officer(in Working Days) | Competent Officer(First Appellate Authority) | Time limit for disposal by the Competent Officer(in Working Days) | Appellate Authority | Time limit for disposal by the Appellate Authority (in Working Days) |
---|---|---|---|---|---|---|---|
1 | Intimation for Payment of initial deposit & EMD | Asst. Secretary in Head Office,Asst. Secretary/ D.D.O in Zonal Offices | 3 working days after receipt of SHLCC/SLSWCC/DLSWCC proceedings | Secretary in Head Office,D.O. & EE, in Zonal Offices | 7 | CEO & EM Head Office | 7 |
2 | Issue of allotment letter | Asst. Secretary in Head Office,Asst. Secretary/ D.D.O in Zonal Offices | 5 working days after payment of initial deposit | Secretary in Head Office,D.O. & EE, in Zonal Offices | 7 | CEO & EM Head Office | 10 |
3 | Issue of confirmatory letter | Asst. Secretary in Head Office,Asst. Secretary/ D.D.O in Zonal Offices | 5 working days after receipt of 100% tentative cost of land | Secretary in Head Office,D.O. & EE, in Zonal Offices | 10 | CEO &EM Head Office | 10 |
4 | Issue of possession certificate | Junior Engineer/Assistant Engineer | 5 working days after issue of confirmatory letter | D.O. &E.E, in Zonal Offices | 7 | CE & CDO Head Office | 7 |
5 | Ececution of lease-cum-sale agreement | Asst. Secretary in Head Office,Asst. Secretary/ D.D.O in Zonal Offices | 30 working days after issue of possession certificate | Secretary in Head Office,D.O. &E.E, in Zonal Offices | 10 | CEO & EM Head Office | 15 |
6 | Issue of NOC in favour of Financial Institutions bank | Asst. Secretary in Head Office,Asst. Secretary/ D.D.O in Zonal Offices | 7 Working Days | Secretary in Head Office,D.O. &E.E, in Zonal Offices | 7 | CEO & EM Head Office | 10 |
7 | Sanction of building plan upto 2 acres | D.O. & E.E. in Zonal Offices | 15 Working days | C.E. & C.D.O. | 7 | CEO & EM Head Office | 15 |
8 | Sanction of building plan more than 2 acres | D.O. & E.E. in Zonal Offices and J.D.T.P in H.O | 30 Working days | C.E. & C.D.O. | 7 | CEO & EM Head Office | 15 |
9 | Sanction of building plan for SUCs | J.D.T.P in H.O | 30 Working days | C.E. & C.D.O. | 7 | CEO & EM Head Office | 15 |
10 | Issue of NOC in favour of KPTCL/ESCOMS | D.O. & E.E. in Zonal Offices | 15 Working days | C.E. & C.D.O. | 7 | CEO & EM Head Office | 15 |
11 | Permission for water supply connection | D.O. & E.E. in Zonal Offices | 15 Working days | C.E. & C.D.O. | 7 | CEO & EM Head Office | 15 |