- Projects above Rs. 15 Crores and upto Rs. 500 Crores will be placed before the State Level Single Window Clearance Committee (SLSWCC).
- Projects above Rs. 500 Crores will be placed before the State High Level Clearance Committee (SHLCC).
Sl.No | Committee | Objectives |
---|---|---|
1 | State High Level Clearance Committee (SHLCC) chaired by Hon’ble Chief Minister, Government of Karnataka | To examine and consider the proposals received from the entrepreneur relating to the industrial and other projects to be set up in the State, with an investment of above Rs.100.00 crores. |
2 | State Level Single Window Clearance Committee (SLSWCC) chaired by the Chief Secretary, Government of Karnataka | To examine and consider the proposals received from the entrepreneurs relating to the industrial and other projects to be set up in the State with an investment of more than Rs.15.00 crores and less than Rs.100.00 crores. |
3 | District Level Single Window Clearance Committee chaired by the Deputy Commissioner of the concerned District | To examine and consider the proposals received from MSME entrepreneurs relating to industrial projects to be set up in the respective Districts with the investment upto Rs.15.00 crores. |
4 | Allotment Committee Chaired by the Chief Executive officer & Executive Member, KIADB | To allot land up to 1.00 acre in Bengaluru Urban District and 2.00 acres in Bengaluru Rural District for MSME Industries in all the sectors with the investment upto Rs.15.00 crores. |
For category of industries
Sl.No | Particulars |
---|---|
(a) |
After approval of the proposed project by the competent Committee/Authority, prescribed application for allotment of land is to be applied online in KIADB website i.e.., www.kiadb.in with Payment of Rs. 250/- is to be made while applying for the online application. List of documents to be uploaded in the online portal while applying the application:
|
(b) |
|
Sl.No | Events Breakup | Working Days |
---|---|---|
1 | Along with the application Initial Deposit to be submitted (30%/20%/10% of the Land Cost) | 30 days from the date of communication |
2 | 70% of land value to be paid. | 90 days from the date of allotment letter. |
80% of land value to be paid. | 150 days from the date of allotment letter. | |
90% of land value to be paid. | 180 days from the date of allotment letter. | |
3 | Obtaining possession certificate | 1 month after confirmation of allotment |
4 | Execution of Lease cum sale deed. | Within one month from the date of possession |